NASA delays shuttle flight to Hubble Space Telescope
Space.com: NASA has pushed back the planned launch of the final flight to overhaul the Hubble Space Telescope by up to five weeks due to external fuel tank delays, mission managers said Thursday.
Space shuttle program manager John Shannon said that the additional time required to include post-Columbia safety improvements in two shuttle fuel tanks supporting the Hubble servicing mission have delayed the spaceflight to no earlier than late September. A seven-astronaut crew was slated to launch toward Hubble aboard NASA's shuttle Atlantis on Aug. 28.
"We really cannot make that date with the external tank processing," Shannon told reporters in a briefing here at NASA's Johnson Space Center. "I really think it's a small price to pay, to tell you the truth, four to five weeks for all the improvements that we're getting on this tank."
Space shuttle program manager John Shannon said that the additional time required to include post-Columbia safety improvements in two shuttle fuel tanks supporting the Hubble servicing mission have delayed the spaceflight to no earlier than late September. A seven-astronaut crew was slated to launch toward Hubble aboard NASA's shuttle Atlantis on Aug. 28.
"We really cannot make that date with the external tank processing," Shannon told reporters in a briefing here at NASA's Johnson Space Center. "I really think it's a small price to pay, to tell you the truth, four to five weeks for all the improvements that we're getting on this tank."